Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?
A . Estimate Costs
B . Control Costs
C . Determine Budget
D . Plan Cost Management

Answer: B