Which process involves developing an approximation of the monetary resources needed to complete project activities?

Which process involves developing an approximation of the monetary resources needed to complete project activities?
A .  Estimate Costs
B .  Control Costs
C .  Determine Budget
D .  Plan Cost Management

Answer: A