Posted by: Pdfprep
Post Date: October 14, 2020
Which process involves developing an approximation of the monetary resources needed to complete project activities?
A . Estimate Costs
B . Control Costs
C . Determine Budget
D . Plan Cost Management
Answer: A
Leave a Reply