PdfPrep.com

Which process in Project Time Management includes reserve analysis as a tool or technique?

Which process in Project Time Management includes reserve analysis as a tool or technique?
A . Estimate Activity Resources
B . Sequence Activities
C . Estimate Activity Durations
D . Develop Schedule

Answer: C

Explanation:

Process: 6.5 Estimate Activity Durations

Definition: The process of estimating the number of

work periods needed to complete individual activities with estimated resources.

Key Benefit: The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.

Inputs

Exit mobile version