Which process in Project Time Management includes reserve analysis as a tool or technique?
A . Estimate Activity Resources
B . Sequence Activities
C . Estimate Activity Durations
D . Develop Schedule
Answer: C
Explanation:
Process: 6.5 Estimate Activity Durations
Definition: The process of estimating the number of
work periods needed to complete individual activities with estimated resources.
Key Benefit: The key benefit of this process is that it provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process.
Inputs