Posted by: Pdfprep
Post Date: November 28, 2020
Which process in Project Time Management includes reserve analysis as a tool or technique?
A . Estimate Activity Resources
B . Sequence Activities
C . Estimate Activity Durations
D . Develop Schedule
Answer: C
Leave a Reply