Which Process Group and Knowledge Area include the Sequence Activities process?
A . Executing Process Group and Project Time Management
B . Executing Process Group and Project Cost Management
C . Planning Process Group and Project Time Management
D . Planning Process Group and Project Cost Management
Answer: C
Explanation:
Knowledge Areas