Which process ensures that provision has been made to address any open issues of risks, with follow-on action recommendations?
A . Closing a Project
B . Controlling a Stage
C . Directing a Project
D . Initiating a Project
Answer: A
Which process ensures that provision has been made to address any open issues of risks, with follow-on action recommendations?
A . Closing a Project
B . Controlling a Stage
C . Directing a Project
D . Initiating a Project
Answer: A