Which process covers the activities of those at the level of management above the Project Manager?

Which process covers the activities of those at the level of management above the Project Manager?
A . Controlling a Stage
B . Managing a Stage Boundary
C . Directing a Project
D . Managing Product Delivery

Answer: C