An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default. However, some materials need to have a different planning horizon.
Which procedure do you recommend for setting the planning horizon?
A . Set the planning horizon in the MRP groups in Customizing and store deviant entries in the material masters for the corresponding materials.
B . Set the planning horizon in the plant parameters in Customizing and store deviant entries in the material masters for corresponding materials.
C . Set the planning horizon in the MRP groups and assign deviant entries via the plant parameter settings in Customizing.
D . Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials.
Answer: D