Which PRINCE2 role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?
A . Project Manager
B . Project Assurance
C . Senior User
D . Senior Supplier
Answer: B
Which PRINCE2 role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?
A . Project Manager
B . Project Assurance
C . Senior User
D . Senior Supplier
Answer: B