Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?
A . Team Manager
B . Project Manager
C . Senior Supplier
D . Team member
Answer: C
Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?
A . Team Manager
B . Project Manager
C . Senior Supplier
D . Team member