Which planning system determines when the necessary labor and equipment will have to be available to perform the work?
A . DRP
B . MPS
C . MRP
D . CRP
E . RCCP
Answer: D
Which planning system determines when the necessary labor and equipment will have to be available to perform the work?
A . DRP
B . MPS
C . MRP
D . CRP
E . RCCP
Answer: D