Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
A . Facilitation techniques
B . Expert judgment
C . Analytical techniques
D . Variance analysis

Answer: C