Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?
A .  Activity cost estimates
B .  Earned value management
C .  Cost management plan
D .  Cost baseline

Answer: A