Posted by: Pdfprep
Post Date: November 20, 2020
Which output is the approved version of the time-phased project budget?
A . Resource calendar
B . Scope baseline
C . Trend analysis
D . Cost baseline
Answer: D
Explanation:
A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget, but excludes management reserves.
Leave a Reply