A company has an asset that has failed and an administrator needs to create a work plan that includes exact steps and descriptions that need to be followed to get the asset in operating status.
Which option does the administrator need to follow?
A . Create follow up work orders
B . Create Job Plan from Work Plan
C . Create a work order and add actuals
D . Create a work order, add tasks and populate the summary field
Answer: D
Explanation:
Reference: https://www.google.com/url? sa=t&rct=j&q=&esrc=s&source=web&cd=9&ved=2ahUKEwiY24aB3u_fAhUMlhQKHUkzDsQQFjAIegQICB AC&url=https%3A%2F%2Fwww.ibm.com%2Fdeveloperworks%2Fcommunity%2Ffiles%2Fform% 2Fanonymous%2Fapi%2Flibrary%2F41abc2d2-e1ec-4709-8b27-4937d78f9909%2Fdocument% 2Fd5e8bd60-bf34-4e12-99d6-9e6181f2dad2%2Fmedia%2F007%2520-%2520Job%2520Plans% 2520Chapter_U1.pdf&usg=AOvVaw08sRWzdeKB2kTOuBsYyi0V