Posted by: Pdfprep
Post Date: April 11, 2021
As part of a new hybrid cloud initiative for a large financial company, the customer technical team is presenting an overview of the current state of the infrastructure and their vision for a new solution.
The project team captures notes during the presentation and adds them to the discovery documentation.
Which of the listed statements is a design constraint?
A . The applications are created in-house with in-guest recovery protection
B . The maximum tolerable data loss is 10 minutes
C . The two data center locations have a network latency of 8 ms round-trip time (RTT)
D . The existing storage is out of maintenance
Answer: D
Leave a Reply