A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal.
Which of the following would the BA classify as a project risk?
A . Customer service ratings will increase with the new system
B . Current infrastructure may not support increased performance
C . Expenditures are currently below budgeted estimates
D . Support calls will increase if the change is not performed
Answer: B