Posted by: Pdfprep
Post Date: November 3, 2020
Which of the following would MOST likely require a risk practitioner to update the risk register?
A . An alert being reported by the security operations center.
B . Development of a project schedule for implementing a risk response.
C . Engagement of a third party to conduct a vulnerability scan.
D . Completion of a project for implementing a new control.
Answer: D
Leave a Reply