Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?
A . Those with high power/influence and no interest in the project.
B . Those with high power/influence and some interest in the project.
C . Those with some power/influence and high interest in the project.
D . Those with some power/influence and some interest in the project.
Answer: B