A network engineer is designing a new IDF in an old building. The engineer determines the equipment will fit in a two-post rack, and there is power available for this equipment.
Which of the following would be the FIRST issue to remediate?
A . Air flow and cooling
B . UPS capability
C . Circuit labeling
D . Power redundancy
Answer: A