A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
A . Sponsor
B . Project manager
C . Project management office
D . Project team
Answer: A
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108