A project manager is reviewing project performance.
Which of the following would be the BEST indicator of the total project cost?
A . AC
B . EAC
C . CPI
D . ETC
Answer: B
A project manager is reviewing project performance.
Which of the following would be the BEST indicator of the total project cost?
A . AC
B . EAC
C . CPI
D . ETC
Answer: B