Which of the following would be the BEST indicator of the total project cost?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project manager is reviewing project performance.

Which of the following would be the BEST indicator of the total project cost?
A . AC
B . EAC
C . CPI
D . ETC

Answer: B