While reviewing the project plan for a new system prior to go-live, an IS auditor notes that the project team has not documented a fallback plan.
Which of the following would be the BEST go-live approach in this situation?
A . Parallel processing
B . Immediate cutover
C . Real-time replication
D . Load balancing
Answer: A