Which of the following would be BEST suited to contribute cost and time estimates for the project activities?

A WBS is being developed for a project.

Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A . Project team members
B . Project sponsor
C . Project manager
D . Project scheduler

Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82