Which of the following ways should the project manager update the risk register?

Risk ID 2 has occurred.

Which of the following ways should the project manager update the risk register?
A . Add a column for probability and set risk 2 at 100%
B . Change the risk 2 response to backups restored
C . Change the risk 2 status to issue
D . Change the risk 2 owner to PM

Answer: A