Which of the following tools or techniques is used for Estimate Activity Durations?
A . Critical path method
B . Rolling wave planning
C . Precedence diagramming method
D . Parametric estimating
Answer: D
Which of the following tools or techniques is used for Estimate Activity Durations?
A . Critical path method
B . Rolling wave planning
C . Precedence diagramming method
D . Parametric estimating
Answer: D