Which of the following tasks is the first to be performed on receipt of a new issue?

Which of the following tasks is the first to be performed on receipt of a new issue?
A . Assess its impact on the project’s objectives
B . Determine whether the issue is a request for change, off-specification or a problem/concern
C . Escalate if it is beyond the delegated authority
D . Identify options to resolve the issue and submit a recommendation

Answer: B