Which of the following tasks are part of the Production support after the Go Live key deliverable? There are 2 correct answers to this question.
A . Resolve issues identified during the Hyper Care period
B . Provide further training to customer end users
C . Set up the Operations Control Center
D . Perform a Technical systems test
Answer: A,B