There are four parallel paths on a network diagram.
The summary duration of each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
A . A, C, G
B . A, B, F
C . D, E, H
D . D, B, F
Answer: C
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 175