PdfPrep.com

Which of the following strategies would be appropriate in order to get the project back on track and that will not compromise customer satisfaction and could still minimse the overall cost of development?

A building project for developing new homes to customers’ own specification is behind schedule and will incur penalty payments if the next milestone is not achieved on time.

Which of the following strategies would be appropriate in order to get the project back on track and that will not compromise customer satisfaction and could still minimse the overall cost of development? Select All that apply.
A . Motivate labour resources to work smarter.
B . Identify activities that are not adding value.
C . Reduce the specification for the project build.
D . Consider increasing the number of builders working on the project each day.

Answer: A,B,D

Exit mobile version