Which of the following steps will need to be completed to continue to use Elastic CoD on the Power System E980?

A customer with a Power System E880C is considering a model conversion to a Power System E980. They currently have Elastic CoD enabled.

Which of the following steps will need to be completed to continue to use Elastic CoD on the Power System E980?
A . Prepay for Elastic CoD usage when placing the upgrade MES order for the Power System E980.
B . Reorder the Elastic CoD enablement features when placing the upgrade MES order for the Power System E980.
C . Reorder the Utility CoD enablement features when placing the upgrade MES order for the Power System E980.
D . Convert static activations to mobile activations when placing the upgrade MES order for the Power System E980.

Answer: A