Which of the following statements on Risk Management in a Scrum project is INCORRECT?

Posted by: Pdfprep Category: SMC Tags: , ,

Which of the following statements on Risk Management in a Scrum project is INCORRECT?
A . The iterative nature of Scrum with its rapid turnaround time and feedback cycles allows for early detection of failures.
B . Risks can be managed only at the project level, even if they are related to or originate in portfolios or programs.
C . Risk Burndown Charts aye an important tool for communicating information related to risks to the Stakeholders.
D . Risk is largely minimized in Scrum due to the flexibility in adding or modifying requirements at any time in the project lifecycle.

Answer: B

Explanation:

Reference: http://blog.scrumstudy.com/how-scrum-framework-minimizes-risks-threats-in-projects-2/

Leave a Reply

Your email address will not be published.