You are the business analyst for your organization. On your current project you’ll be using the change-driven approach for defining requirements and gathering feedback.
Which of the following statements best describes the change-driven approach?
A . The change-driven approach favors defining requirements through experimentation.
B . The change-driven approach favors defining requirements standardized templates.
C . The change-driven approach favors defining requirements through team interaction.
D . The change-driven approach does not define the requirements until after a solution for the problem has been identified.
Answer: C
Explanation:
The change-driven approach looks to create business value in short iterations. The downside of this approach, however, is that there is more risk and uncertainty in the overall direction. The change-driven approach relies on team interaction to define requirements and gather feedback on the solution.
Answer. B is incorrect. The plan-driven approach relies on standardized templates, not the change-driven approach.
Answer. A is incorrect. This is not a valid description of the change-driven approach.
Answer. D is incorrect. Requirements may evolve through the change-driven approach, but they are still identified early in the business analysis work. The requirements must be identified so that the business analysts know what solution would satisfy the requirements.