Which of the following statements about the planning functions available in SAP ECC is correct?

Which of the following statements about the planning functions available in SAP ECC is correct?
A . Master production scheduling (MPS) refers to preferred planning of important materials.
B . Material requirements planning (MRP) includes automatic capacity leveling.
C . Long-term planning (LTP) is a long-term form of forecast planning.
D . In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.

Answer: A