Which of the following statements about lines of authority and reporting are true?
The Project Manager has day-to-day control for a management stage within the limits laid,
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
A . Only 1 is true
B . Only 2 is true
C . Both 1 and 2 are true
D . Neither 1 or 2 are true
Answer: C