A project’s business requirements require that the new solution reduce the labor costs currently attributed to performing end of month accounting procedures. Currently the company routinely must pay overtime to meet the deadline. The business analyst (BA) has been documenting the process and wants to ensure that the approach to the process design is feasible for the staff who perform the end of month procedures.
Which of the following stakeholders will provide this verification?
A . Implementation subject matter expert
B . Domain subject matter expert
C . Operational support
D . Project sponsor
Answer: C