Which of the following shows the correct sequence of planning tasks?
A = Determine DR strategy.
B = Determine the need for Virtualization.
C = inventory of current situation.
D = Calculate capacity requirements.
E = Determine the backup strategy.
F = Estimate future growth.
A . B-D-C-F-E-A
B . C-D-B-A-F-E
C . C-D-F-B-A-E
D . A-B-E-C-D-F
Answer: C