A project team is distributed across multiple countries, and they are having issues agreeing on what is being delivered and how it should be developed.
Which of the following should the project manager do to alleviate some of the tension between team members, break down cultural barriers, and improve communication?
A . Ask the team to communicate only through email to clearly document issues.
B . Discuss this issue with senior management and recommend that the team be co-located.
C . Monitor performance and discuss the issues in detail at the next retrospective.
D . Hold daily standup meetings with the two teams at a time that works best for everyone.
Answer: D