A project in the execution phase is over budget, and tasks on the critical path are on schedule.
Which of the following should the project manager do NEXT?
A . Update the project management plan.
B . Issue a change request.
C . Revise the project charter.
D . Evaluate the impact to the baseline.
Answer: D