Posted by: Pdfprep
Post Date: December 17, 2020
The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the following should the project manager do NEXT?
A . Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
B . Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
C . Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
D . Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
Answer: C
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238
Leave a Reply