Which of the following should be the PRIMARY focus of a risk owner once a decision is made to mitigate a risk?

Which of the following should be the PRIMARY focus of a risk owner once a decision is made to mitigate a risk?
A . Determining processes for monitoring the effectiveness of the controls
B . Confirming to management the controls reduce the likelihood of the risk
C . Updating the risk register to include the risk mitigation plan
D . Ensuring that control design reduces risk to an acceptable level

Answer: D