Posted by: Pdfprep
Post Date: December 24, 2020
An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?
A . PMO
B . Project sponsor
C . Project coordinator
D . HR
Answer: B
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82
Leave a Reply