A major stakeholder wants to know how the implementation of new features in the development of a product is progressing.
Which of the following should be reported to the stakeholder?
A . Number of requirements tested and approved
B . Distribution of project changes
C . Requirements status during the project development cycle
D . Number of requirements approved vs. number of requirements rejected
Answer: A