Which of the following should be noted when upgrading the E9000 server compute node? (Multiple choice)

Which of the following should be noted when upgrading the E9000 server compute node? (Multiple choice)
A . It is recommended to upgrade the BMC software system and then upgrade the BIOS
B . When upgrading the BIOS, it is recommended to power off the business system first
C . In the process of upgrading, do not power on the business system, restart and other operations
D . During the upgrade process, it is forbidden to plug in the calculation node

Answer: ABCD