Which of the following should be included in the scope statement?

The managing director of a law firm has asked the project manager to create a scope statement for a new contract.

Which of the following should be included in the scope statement? (Choose two.)
A . Scope creep
B . Deliverables
C . Business requirements
D . Project schedule
E . Gate review
F . Key performance indicators

Answer: BC