Which of the following risks should be given highest priority?
A . Risks which have a high impact and which may arise occasionally
B . Risks which have a low impact but which arise frequently
C . Risks which have a high impact and have a low likelihood of arising
D . Risks which have a low impact and a low likelihood of arising
Answer: A