Posted by: Pdfprep
Post Date: October 31, 2020
A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling.
Which of the following resources has the authority to authorize this change?
A . Stakeholders
B . Scrum master
C . Project sponsor
D . Project team
Answer: D